LanguageENعربيTR
Start a project

Who installs hotel FF&E, and what happens if it arrives damaged

· Bravo Furniture

Short answer

In the US, much hotel FF&E is installed by specialist firms from the moving trade, and one furniture maker calls installation by the maker a rarity. Where the seller’s risk ends is set by the Incoterms rule in the contract. Damage has to be noted at delivery: hidden damage must be reported in writing within seven days for road carriers under CMR, and within three days for sea carriers under the Hague-Visby Rules.

Who usually installs hotel FF&E

In the United States much of this work is done by the moving trade. Corrigan Logistics, a member of the UniGroup Logistics Network, says its crews receive the product on site, unpack it, install it and remove the debris [1]. Meyer sells hospitality FF&E services under its moving services, covering “the full scope, from warehouse receiving through installation” [2]. BRG Office Movers, a division of Beltmann Relocation Group, lists receiving and inspecting, warehousing, assembly and room-by-room staging [3]. Flood Brothers, a commercial relocation firm, receives, warehouses, stages and installs with its own crews [4].

Makers that install their own work are fewer. Artone, a hospitality furniture maker, writes that some makers offer installation, “though a rarity in FF&E production”, and names three routes: the maker, an installer the maker recommends, or an independent installer [5].

How Bravo runs the whole job, through to installation

Bravo Furniture is one of the makers that install. Our technical office draws the shop drawings for approval, and a full mock-up room is built to the approved drawings for the brand or consultant to inspect before production. Joinery, casegoods, upholstery and finishing are done in our own factory in Turkey and checked against the drawings before packing. Then come export packing and shipping to site, and our team installs the rooms and hands them over.

Bravo made and installed the hotel furniture for Hilton Dammam Airport, DoubleTree by Hilton Jeddah and Hilton Garden Inn Jeddah Al Nuzhah, each after a mock-up room, and for the guest rooms, suites and public areas of Hilton Garden Inn Jeddah Falastin.

The contract sets where our scope stops. At Citadines Maslak in Istanbul it included shipment and assembly, from April to June 2024. At Moonlight Hotel in Jeddah, Bravo drew, sampled, made and packed the furniture, and the owner handled freight and assembly.

Turnkey fit-out

The receiving step between the container and the room

Between the factory and the finished room there is usually a receiving step. Corrigan inspects products as they arrive, logs them in its warehouse system, then delivers to site just in time [1]. Lifetime Moving & Storage inspects every delivery against the purchase order, photographs any damage and reports it within 24 hours [6].

Flood Brothers explains why freight sent straight to a building site goes wrong: “An active construction or renovation site usually has no dock, no secure storage, and no one available to receive, count, and inspect freight” [7]. Through a consolidation warehouse, it says, short shipments and wrong items show up weeks before installation, “leaving time to reorder” [7].

Each extra handling leg is another chance to mark a finished edge. If the goods go to a warehouse, agree who inspects there and on what form.

The claim window closes at receiving

Lifetime Moving & Storage puts it in one line: “Damaged items that were not caught at receiving cannot be claimed” [6]. The deadlines come from the transport conventions.

On international road freight, the CMR Convention says that if the consignee takes delivery without noting reservations, at delivery for visible damage or within seven days, Sundays and public holidays excepted, for damage that is not visible, that is prima facie evidence the goods arrived as the consignment note describes them. Reservations for hidden damage must be in writing [8].

Sea freight runs on a shorter clock. Under the Hague Rules, notice of loss or damage goes to the carrier in writing at the port of discharge, before or at the removal of the goods, or within three days if the damage is not visible [9]. The Visby amendment gives one year from delivery to bring suit [10]. A crate first opened weeks into an installation is outside both windows.

What a road carrier owes

CMR compensation is set by weight, not value. Since the 1978 Protocol it cannot exceed 8.33 units of account, the IMF’s special drawing rights, per kilogram of gross weight short [11]. It is calculated on the value of the goods at the place and time they were accepted for carriage [8]. A light, costly lacquered door recovers far less of its value under that cap than a heavy stone top.

The carrier is also relieved of liability for damage caused by missing or defective packing [8]. So the crate specification belongs in the quote, and cargo insurance belongs in the contract.

Where the seller’s risk ends

Four Incoterms 2020 rules cover most hotel FF&E contracts. The table follows the ICC Academy, the International Chamber of Commerce’s training arm [12][13][14], and the ICC’s own summary [15]. The ICC Academy advises using FCA rather than EXW, and DAP rather than DDP, where possible [12].

RuleWhere the seller’s risk endsWho clears importWho unloads at destination
EXW (Ex Works)At the seller’s premises. Loading is the buyer’s risk and costThe buyerThe buyer
FCA or CIPWhen the goods are handed to the carrier at the named place. Under CIP the seller insures to Institute Cargo Clauses (A)The buyerThe buyer
DAP (Delivered at Place)At the named destination, ready for unloading. The buyer carries the risk during import clearanceThe buyerThe buyer
DPU (Delivered at Place Unloaded)At the named destination, after the seller has unloadedThe buyerThe seller
DDP (Delivered Duty Paid)At the named destinationThe sellerThe buyer

Four sourcing routes compared

Who may install in Germany

Some countries regulate the fitting trade. In Germany, Tischler (joiner) is number 27 in Annex A of the Handwerksordnung, the list of crafts that need registration to be carried on independently [16]. Ask a local adviser whether your installation scope needs a registered firm.

Hotel FF&E for Europe

What the cartons and the contract should say

A receiving warehouse sorts by what is printed on the box. A 2019 bid from the College of DuPage, Illinois, for its hotel’s guestroom furniture tells the maker to mark the outside of each package with the property name, item name, purchase order number, specification number and area [17].

The Beloit procurement request makes field measurements for custom items the fabricator’s job, and makes the purchasing agent check with the owner and contractor that items fit lifts, corridors and doorways [18]. Its final punch list combines the notes of the designer, the purchasing agent, the owner and the installer [18].

  • Which Incoterms 2020 rule applies, with the named place written in full?
  • Do the goods go to a receiving warehouse or straight to site, and who pays for storage?
  • Who inspects on arrival, on what form, and within how many hours is damage reported in writing?
  • Who files a freight claim, and against whom?
  • Does the cargo insurance run to the installation address?
  • Which firm is entitled to install in the destination country?
  • Who takes field measurements for fixed work?
  • Who compiles and signs the punch list, and what does closing it release?

Questions

Does the furniture maker install the furniture?
Often not. In the US, much hotel FF&E is installed by specialist firms from the moving and relocation trade. Some makers install their own work. Bravo is one: our team installs the rooms and hands them over, and the contract sets the scope.
What happens if a wardrobe arrives damaged?
It depends on when the damage is found. Under the CMR Convention for road freight, reservations go to the carrier at delivery for visible damage and in writing within seven days for hidden damage. Under the Hague-Visby Rules for sea freight, notice is due at removal or within three days, and suit within one year.
Who carries the risk while the goods are in transit?
The Incoterms rule in the contract. Under EXW the risk passes at the seller’s premises. Under DAP it passes at the named destination, ready for unloading, and the buyer unloads and clears import. Under DPU the seller also unloads. Under DDP the seller handles import formalities.

Related projects

Related pages

More guides

Sources

  1. Corrigan Logistics: hospitality installation
  2. Meyer: hospitality FF&E services
  3. BRG Office Movers: hospitality FF&E services
  4. Flood Brothers: FF&E installation
  5. Artone: hotel FF&E installation guide
  6. Lifetime Moving & Storage: FF&E services
  7. Flood Brothers: How to manage FF&E logistics from procurement to installation
  8. UNIDROIT: CMR Convention, 1956 (full text)
  9. Admiralty and Maritime Law Guide: Hague Rules, 1924 (text)
  10. Admiralty and Maritime Law Guide: Visby Rules, 1968 (text)
  11. University of Oslo: Protocol to the CMR Convention, 1978 (text)
  12. ICC Academy: Incoterms 2020, EXW or DDP
  13. ICC Academy: Incoterms 2020, DAP or DDP
  14. ICC Academy: Incoterms 2020, DPU or DAP
  15. International Chamber of Commerce: Incoterms 2020
  16. buzer.de: Handwerksordnung, Annex A
  17. College of DuPage: bid for Inn at Water’s Edge lobby and guestroom furniture (PDF, 2019)
  18. Ho-Chunk Nation: Procurement Services RFP for the Beloit development (PDF, 27 September 2024)

Start your next project

Send us your brief, drawings or a Pinterest board. We come back within 48 hours with a costed proposal and indicative lead times.