Phased hotel refurbishment: floor by floor or all at once

· Bravo Furniture

Short answer

A hotel refurbishment runs in one of two shapes. Either the hotel stays open and the work moves floor by floor, or the hotel closes and all the work is done at once. Both are in use, and the shape changes how the furniture is packed, delivered, stored and checked, so settle it before you ask for prices.

The two shapes side by side

A price written for one shape is wrong for the other, so name the shape in the first conversation.

What changesOpen, floor by floorClosed, one programme
DeliveriesSeveral dated deliveries, each holding one floorOne delivery, or a short run of them
PackingCartons grouped and marked by floor and roomCartons grouped by room type or item
StorageA place to hold later floors while earlier ones are fittedSite space for everything, inside one window
Import papersA set for each consignment, each with its own time limitFewer sets, issued close together
SnaggingA snag list for each floor, closed before the floor goes back on saleOne snag list for the whole hotel, walked at the end
Rooms off saleOne floor at a timeThe whole hotel, until it reopens

Both shapes are in use

In the UK, a 301-bedroom Delta by Marriott in Bristol was renovated "over 10 phases whilst the hotel was in operation", according to David Elliott, project manager at County Contractors, writing on the furniture maker's project page [1].

In the US, Keith Shugerts of Essex Hotel Management told Hotel Management in September 2024 that his team works from the top down. "We take a whole floor out," he said, starting at the top of the property and working down to the first floor. The crews stay on the active floor, so guests rarely see them [2].

Other US owners now close instead. Miraj Patel, president of Wayside Investment Group, said in August 2025: "we actually come in, shut the hotel down and do it all at once, instead of doing floor-by-floor". He said floor-by-floor work disturbs guests, pulls down the hotel's online score and takes longer [3]. Scott Hammons of Ground Level said that six or seven years ago owners spread the work out to keep hotels open, and that now many more want to "get in and out" [3].

What phasing changes in the furniture order

Each delivery has to hold everything one floor needs, and nothing from the next. So cartons are grouped and marked by floor and room number, and a floor can be released without anyone opening boxes to find it.

Someone has to hold the later floors while the first ones are fitted: a warehouse near the hotel, or space inside it. Either way it costs money, so name the place and who pays for it in the contract before the first load leaves.

On our own jobs, floors or room types can ship separately. El Ajou left in seven shipments and Al Obeikan in three containers.

Distance matters more when there are several deliveries. From Turkey to Western Europe, road freight is counted in days and sea freight in weeks, so a floor that misses one truck can follow on the next. Our Europe and UK page sets out the times.

Hotel FF&E for Europe

Inside one floor, the order is fixed

Modern Hospitality, a UK trade title, set out the order in June 2026: "Carpet has to be down before headboards go on, joinery has to be in before soft furnishings are dressed, and the final snag walk needs the room functionally complete." Items that arrive out of order make trades work around each other, which "quietly eats two weeks out of the schedule" [4].

The same article names three ways deliveries go wrong. Items arrive too early and clog the site, arrive too late and stall the work, or get damaged after being handled through three storage places on the way in [4]. Plan each floor's furniture backwards from its carpet date.

It also states the cost: "In hospitality, a closed room is a liability. It earns nothing, costs to maintain, and every night it stays out of the system is revenue you can't recover." [4] A delivery that is a week late keeps every room on that floor off sale for that week.

Match the delivery rate to the sign-off rate

Hans Peter Betz, writing on LinkedIn, described a hotel whose FF&E schedule had been approved two years earlier and never updated: "The original commissioning plan called for a three-week snag-and-sign-off window across all 420 keys. At the rate the furniture was moving, that window was going to open with 180 rooms capable of receiving it." [5]

A phase plan should make the two rates the same, floor by floor, so that a gap shows in the first month and not the last.

Import papers on a long programme

Each consignment needs its own A.TR movement certificate, and for furniture from Turkey to the EU each one has four months from issue to reach the customs office of the importing country [6]. On a programme that runs from spring to autumn, that means one set of papers for every delivery, each raised at dispatch.

FF&E lead times guide

Five questions that settle the shape

Answer these with the enquiry. They turn a delivery date into a delivery plan.

  • Will the hotel trade through the works, or close?
  • How many phases, and is each one a floor, a wing or a room type?
  • Who holds the goods for later phases, where, and at whose cost?
  • By what date must each phase be finished, and when does it go back on sale?
  • Who walks and closes the snag list on each floor?

Questions

Can a hotel be refurbished while it stays open?
Yes, and the usual unit is the floor. A 301-bedroom Delta by Marriott in Bristol was renovated over 10 phases while it traded. Essex Hotel Management in the US works from the top floor down, one floor at a time.
Is it better to close the hotel and do it all at once?
Some owners now think so. Wayside Investment Group shuts its hotels and renovates at once, saying floor-by-floor work disturbs guests and takes longer. Which shape suits a hotel depends on its trade and its reopening date, and it changes the furniture order enough to settle before pricing.

Related projects

Related pages

More guides

Sources

  1. Curtis Furniture: Delta by Marriott, Bristol City Centre, project page with a County Contractors statement
  2. Hotel Management: Hospitality How-To, oversee a PIP or renovation (Jena Tesse Fox, 3 September 2024)
  3. Hotel Management: What hotel investors think about capex in 2025 (Patricia Kirk, 28 August 2025)
  4. Modern Hospitality: The room-ready countdown (14 June 2026)
  5. Hans Peter Betz: The FF&E schedule was approved in year two. Nobody updated it in year four (LinkedIn)
  6. EC-Turkey Customs Cooperation Committee: Decision No 1/2006, A.TR movement certificates (EUR-Lex)