Short answer
When a hotel project moves furniture out of Asia, Italy, Portugal and Turkey are often on the same shortlist. Into the EU, duty does not separate them: furniture from Turkey enters at 0% inside the EU-Turkey customs union. What does separate them is capacity in your time window, how much of the room one contract covers, the trip to the mock-up room, and one customs step that a Turkish order adds.
The shortlist after Asia
Shawn Fowler of Canoe Hospitality, a US hospitality procurement firm, wrote in April 2025: "Meanwhile, Turkey is gaining traction beyond textiles, emerging as a player in casegoods and seating production." [1]
Nicole Schmidt of Source, another purchasing firm, set the limit on any move away from Asia: "While large-scale shifts in production regions are unlikely due to capacity limitations outside of Asia, ongoing diversification efforts will help purchasing agents balance cost, quality, reliability and scheduling issues." [2] So the useful question is narrower than the country. Ask which factory has free capacity in your window, and who signs off the finish.
Five points to compare
Each row ends with the document or step that settles it, so it does not rest on either side's word.
| Point | Portugal or Italy | Turkey | How to check |
|---|---|---|---|
| Duty into an EU country | 0%, inside the single market | 0%, inside the EU-Turkey customs union, with an A.TR per consignment | Ask each bidder which document travels with the goods |
| Proof of origin | EU origin of the goods | A certificate of origin, separate from the A.TR | If a tender needs origin, write origin into the request |
| Customs step | None between EU countries | One export and import clearance | Ask for it as a line on the programme |
| Trip to the mock-up room | Short for a European buyer | A flight to Istanbul or Bursa for most buyers | Book both visits and compare time and cost |
| Sea time to northern Europe | Not needed for nearby sites; trucks within the EU cross no customs border | 12-19 days from a port near Bursa on one carrier's 2026 service map | Ask a forwarder for current sailings |
Duty is level; the customs step is not
Furniture is an industrial product, and industrial goods in free circulation move inside the EU-Turkey customs union with an A.TR movement certificate [3]. So a Portuguese or Italian factory has no duty advantage over a Turkish one when the hotel is in the EU.
What a Turkish order does add is a border. Arcedior, an FF&E sourcing firm, writes: "Cross-border projects from India, China, Turkey, or the UAE should add 2-4 weeks for consolidation and customs clearance." [4] A shipment from Italy or Portugal to another EU country has no such step. Put it on the programme as a named line.
What one contract covers
A hotel package split between a casegoods factory, an upholstery shop, a lighting supplier and a fit-out contractor has four boundaries to manage. Ask each bidder to fill in the same responsibilities matrix, and read the boundaries side by side.
At Bravo, furniture, joinery, wall panels and doors come from one team, for a new hotel or a renovation, and the contract sets where our scope stops. Export packing, logistics and installation on site are done by our own team.
Italy and Portugal in their own published numbers
Italy is the largest of the three industries here. The study centre of FederlegnoArredo, the Italian wood and furniture federation, put the Italian wood-furnishing chain at €52.2 billion of production revenue in 2025, with more than 62,000 companies and more than 292,000 employees. The furniture part alone had turnover above €27.7 billion, of which €14.2 billion was exported. France, the US and Germany were the top three markets (economic note of 8 April 2026) [5].
Portugal is smaller and sells mostly abroad. Wood and furniture exports reached €2,956 million in 2025, 2% below 2024, with Spain taking 35% and France 25% (AIMMP figures, reported 11 March 2026) [6]. Eurostat counts 4,545 Portuguese furniture makers in 2024, employing 36,863 people, with turnover of €2.66 billion; Italy's furniture makers had turnover of €26.9 billion the same year [7].
Portuguese makers have pushed into hotels in the US. AIMMP took 14 furniture companies to Boutique Design New York in 2023 [8], and 12 companies to HD Expo in Las Vegas in 2026 [9].
CSIL puts European production of contract furniture and furnishings above €13.5 billion, with hospitality the second-largest segment. Its list of the main producing countries is the UK, Italy, Germany, Poland and Sweden (June 2025) [10].
None of these sources publishes a price or a lead time for a hotel order, in any of the three countries. Ask each bidder to price the same specification, with dates counted from a named event.
Sea times from the Sea of Marmara
Ocean Network Express runs its Aegean Express (AEX) service from a container port on the Sea of Marmara near Bursa. In its 2026 Intra-Europe service map, the sea time from that port is 12 days to Felixstowe, 15 to Hamburg, 17 to Bremerhaven and 19 to Antwerp [11]. The service has no Rotterdam call.
Ports change. On 20 July 2026 Maersk announced that its SLC Aegean Sea service would call Wilhelmshaven instead of Hamburg, from the sailing of 6 September 2026 [12]. Ask a forwarder for current sailings before you fix a delivery date.
For a US hotel
From a US site, Turkey, Portugal and Italy are all an ocean away. Alan Benjamin and Sarah Churchill of Benjamin West, a purchasing firm, wrote in August 2023: "When the client directs the project team to have items in the model room sourced from a minimum of two vendors per specification/commodity, and ideally from two countries of origin, it allows for multiple options and the ability to pivot as needed." [13] That choice is made at the model room, before the full order.
US duty depends on the tariff line and the country. Our US page and our Turkey or China guide set out the rates we read on 9 November 2026.
Questions
- Do we pay duty on hotel furniture from Turkey into the EU?
- No. Furniture moves inside the EU-Turkey customs union with an A.TR movement certificate, so it enters any EU country at 0%. Import VAT is still due in the country of import.
- How much time does the border add against a European supplier?
- Arcedior, an FF&E sourcing firm, advises adding 2-4 weeks for consolidation and customs clearance on cross-border projects from Turkey. A shipment between two EU countries has no customs step. Put the step on the programme as its own line.
Related pages
More guides
- Hotel furniture from Turkey or Poland
- Who supplies hotel FF&E in the Gulf: named firms on published facts
- Import requirements for hotel furniture from Turkey, by destination
- What FF&E covers in a hotel, and where the line sits
- Equipping a hotel: five purchases, five kinds of supplier
- How hotel FF&E procurement runs, seen from the factory
Sources
- Shawn Fowler, Canoe Hospitality: Staying the course, why tariffs won't derail hospitality FF&E (LinkedIn, 16 April 2025)
- Hotel Business: Purchasing companies report, 2025 Green Book
- European Commission, Access2Markets: EU-Türkiye customs union
- Arcedior: Hotel FF&E sourcing company, what they do and when to hire (updated 16 June 2026)
- FederlegnoArredo study centre: Economic note for the 64th Salone del Mobile.Milano (PDF, 8 April 2026)
- ECO: Exportações de madeira e mobiliário recuam 2% em 2025 (11 March 2026)
- Eurostat: Enterprise statistics by size class and NACE activity, sbs_ovw_act, NACE C31 (updated 30 September 2026)
- Mobiliário em Notícia: EUA, em 10 anos 10 vezes mais exportações nacionais (22 November 2023)
- Mobiliário em Notícia: Portugal strengthens its presence at HD Expo 2026 (14 May 2026)
- World Furniture Online, CSIL: An update on the contract furniture and furnishings market in Europe (June 2025)
- Ocean Network Express: Intra-Europe service map, AEX (PDF, 2026)
- Maersk: SLC Aegean Sea service, Wilhelmshaven update (20 July 2026)
- Alan Benjamin and Sarah Churchill, Benjamin West: Overcommunicate for CapEx project success (Hotel Investment Today, 7 August 2023)